Phase Cost Estimates
Detailed cost breakdown for each build-out phase - FSS Colocation Center (2,100 sq ft)
Phase 1 Cost
$266,250
1,050 sq ft | 20 racks
Phase 2 Cost
$221,250
1,050 sq ft | 20 racks
Shared Infrastructure
$44,000
One-time costs
Grand Total
$584,650
Including 10% contingency
Phase 1 - Initial Build-Out
Initial 42ft x 25ft (1,050 sq ft) colocation space with full infrastructure
1,050 sq ft20 racksTotal: $266,250
Electrical Systems
Main Electrical Panel & Distribution$18,000
UPS System (40kVA)$22,000
PDUs (20 racks)$16,000
Transfer Switches$4,000
Wiring & Conduit$8,000
Subtotal$68,000
Fire Suppression
FM-200 Clean Agent System$25,000
VESDA Detection$8,000
Panels & Controls$4,000
Subtotal$37,000
Server Infrastructure
42U Server Cabinets (20)$30,000
Hot/Cold Aisle Containment$12,000
Cable Management$5,000
Subtotal$47,000
Cooling Systems
CRAC Units (2x)$18,000
Containment Panels$8,000
Temperature Monitoring$3,000
Subtotal$29,000
Network / Connectivity
Frontier 10G Fiber Install$5,000
Network Switches$12,000
Structured Cabling$9,000
Meet-Me Room Setup$4,000
Subtotal$30,000
Build-Out / Construction
Raised Floor (1,050 sq ft)$26,250
Walls & Partitions$15,000
Security Systems$8,000
Permits & Inspection$6,000
Subtotal$55,250